Construction Updates

Friday, November 22, 2024

November 21, 2024

Exciting Progress at The Heights of Harmony!

We are excited to share the incredible progress at our Oshawa project! In Phase 1, all curb and sidewalk work is complete. The driveway base coat is done, and we’re laying sod this month. Over in Phase 2, over 60% of the rough framing and masonry work is complete, and the interiors of 40+ units are fully finished.

Older

Monday, August, 26, 2024

Phase 2 taking shape!

We are pleased to report significant progress at The Heights of Harmony Phase 2. We have successfully framed 6 blocks of Rear Lane Towns and 4 blocks of Back to Back Towns. Of these, 50% have completed electrical rough-ins, and 40% have finished drywall and taping.

Additionally, we are in the process of installing natural gas and hydro services throughout the site. Road construction is scheduled to commence in mid-September.

Monday, May, 27, 2024

We’re excited to share some updates on our construction progress!

Phase 1 has reached 75% completion, unveiling the beautiful streetscapes and harmony within this master-planned community. While construction has also begun on Phase 2! Looking ahead, the curb and sidewalk program is set to start at the end of next month, further enhancing our community's infrastructure. Stay tuned for more updates as we continue to move forward.

Friday, August, 25, 2023

We are excited to bring you the latest update on the construction of The Heights of Harmony Phase 1.  We have made significant advancements, showcasing our commitment to delivering a high-quality project that aligns with our timeline and vision.

Foundation Completion

We are pleased to announce the successful installation of all foundations required for the project. This critical phase is complete, setting a solid base for the upcoming stages of construction.

Framing Milestone

Our construction team has made significant headway in the framing phase. More than 50% of the framing work has been initiated, showcasing the shape and structure of the community as it takes form.

Roofing Achievement

Among the framed sections, an impressive 50% have already reached the roofing completion stage. The roofs provide not only protection but also a tangible representation of the project's advancement.

Exterior Cladding Commencement

Simultaneously, the commencement of exterior cladding installation is underway. The installation of materials and textures is beginning to emerge, giving life to the envisioned design aesthetics of each lot. Our team is diligently working to ensure that the cladding aligns with our design vision.

As we move forward, we remain focused on maintaining our momentum. We deeply appreciate the collaborative efforts of everyone involved. We will continue to provide regular updates as we approach the next milestone.

Monday, June, 26, 2023

Minto Communities team has marked the important milestone of the official ground-breaking of Heights of Harmony Phase 1! We are so excited to see construction begin, knowing that we are laying the foundation for a community that will stand for generations to come.

Wednesday, July, 06, 2022

Construction progress has begun at The Heights of Harmony! Site servicing has started in preparation for Phase One construction!

All plans, dimensions and specifications are subject to change without notice. Actual usable floor space may vary from the stated floor area. Column locations, window locations and size may vary and are subject to change without notice. Renderings are artist’s concept and will change if required by site conditions. Plans, specifications and materials are subject to availability, substitution, modification without notice at sole discretion of Minto Communities Inc. E. & O.E. October 2019.

Harmony Rd. N. and Winchester Rd. E. in North Oshawa

The Heights of Harmony Sales Centre

 

Site Location:
Harmony Road North,
Oshawa, ON, L1H 8L7

Open with Google Maps

Hours of Operation

Monday-Thursday: 11AM-5PM
Friday: By Appointment Only
Saturday-Sunday: 11AM-5PM
 

All plans, dimensions and specifications are subject to change without notice. Actual usable floor space may vary from the stated floor area. Column locations, window locations and size may vary and are subject to change without notice. Renderings are artist’s concept and will change if required by site conditions. Plans, specifications and materials are subject to availability, substitution, modification without notice at sole discretion of Minto Communities Inc. E. & O.E. March 2023.

To view this community's Home Construction Regulation Authority (HCRA) license, click here.

Register now for special offers, incentives and latest news