Construction Updates

Tuesday, June 27, 2023

The Saint: Construction Update Delivers Progress

We've got some exciting news to share about our progress on the building. Here's the scoop:

Level 16 Update

We're in full swing, laying rebar and pouring concrete like there's no tomorrow! The structure is shaping up nicely, and we're making sure everything is perfect. Plus, we're coordinating all the mechanical and electrical work to be started soon.

Window Wonderland

The windows for the entire building are ready to go. No delays, hooray! We're delivering them to the site and installing them as the concrete keeps climbing. We're currently at level 7.

Elevating to New Heights

Our construction hoist is doing some heavy lifting, bringing both material and manpower up to level 9. We've got the hustle going on, and soon we'll be extending it all the way up to level 13. The sky's the limit, quite literally!

Parking Garage Pizzazz

The parking garage has received a fresh coat of paint, making it look snazzy and ready to welcome your vehicles. Safety and style, all in one place!

Drywall Delight

Our drywall contractor is on-site, working their magic. They're busy laying out suites and corridors up to level 5. It's like a puzzle, and they're putting all the pieces together flawlessly. Once they're done, the finishing trades will come in and add that extra shine.

Stay tuned for more exciting progress as we bring this magnificent project to life. We appreciate your support and can't wait to unveil the finished masterpiece. 

Older

Monday, January, 23, 2023

The Downtown Toronto core is growing, and The Saint is at the center of it. 

Construction continues to progress with formwork now completed on level 9! Our construction hoist is installed and ready for our first window installation. The structural stud and metal team is working their way up the building and below ground the interior walls are being installed.

The behind-the-scenes team including, plumbing, electrical, sprinkler and HVAC is working hard on finalizing plans to start work after formwork is completed. 

It won’t take long before you will begin to see The Saint tower rise up from the site! 

Wednesday, July, 07, 2021

Construction is well underway at The Saint, and we are happy to announce that the crane has been installed!

Walk by Church and Adelaide to see the new addition for yourself or watch the full video and be a part of this exciting new milestone.

Tuesday, June, 29, 2021

Minto Communities GTA's new condo tower at Church and Lombard streets in Downtown Toronto is gearing up for the next step in its construction. Having bottomed out six levels deep earlier this month, the pit is being readied for crane installation. A square notch has been carved out of the base of the pit and filled with rebar, and a photo captured this past weekend shows a concrete pump positioned at the street-level edge of the pit with its boom extended, filling the notch and rebar cage with concrete to form the footing for the tower crane.

Tuesday, January, 19, 2021

Construction continues to progress at The Saint site, as our team has worked into the New Year and looks ahead at what is to come. 

Following the completion of site preparation by our excavation contractor, the shoring trade mobilized to site at the end of October and began the process of splicing the piles. Drilling of piles started on November 12th and was completed just before December 25th. 

Our excavation contractor has remobilized to site at the end of December and the excavation work has been ongoing since January 4th.

The excavation and shoring work will continue until early July 2021 where the formwork contractor would mobilize to site for the erecting the tower crane and start of Formwork.

Be sure to check back here to get more construction updates on the Saint! 

Monday, September, 14, 2020

The Saint celebrated the ceremonial groundbreaking event this past month. While construction hasn’t officially begun, there’s been a lot of site preparation underway. The demolition is still ongoing at the site and with a scheduled demobilization at the beginning of October. The actual construction will start shortly thereafter depending on site conditions. This will precede approximately two weeks of work in between the excavation contractor preparing the site and building platforms for the drill rigs and the shoring contractor splicing the piles. Once that’s completed, the drilling process will begin. There’s lots to look out for in the future, be sure to follow along!

All plans, dimensions and specifications are subject to change without notice. Actual usable floor space may vary from the stated floor area. Column locations, window locations and size may vary and are subject to change without notice. Renderings are artist’s concept and will change if required by site conditions. Plans, specifications and materials are subject to availability, substitution, modification without notice at sole discretion of Minto Communities Inc. E. & O.E. October 2019.

Community Logo

Adelaide St. E. and Church St. in Downtown Toronto

The Saint Sales Centre

Minto Communities GTA Presentation Centre
534 Queen St. W.,
Toronto, ON, M5V 2B5

Site Location:
89 Church St.,
Toronto, ON, M5C 2G3

Open with Google Maps

Hours of Operation

By Appointment Only.

Contact

Email

Facebook Twitter Instagram Youtube Linked In TikTok

All plans, dimensions and specifications are subject to change without notice. Actual usable floor space may vary from the stated floor area. Column locations, window locations and size may vary and are subject to change without notice. Renderings are artist’s concept and will change if required by site conditions. Plans, specifications and materials are subject to availability, substitution, modification without notice at sole discretion of Minto Communities Inc. E. & O.E. March 2023.

Register now for special offers, incentives and latest news